June 22-July 26, 2024 Operations Report
/Nick Kluge, Operations Manager
During this period:
Routine aquatic plant management in Dickinson Lake
New siren installation and testing at the LISECC Maintenance Shop
Backup generator manually cycled
Customer Water Usage Survey
Deployed aluminum marina docks
Calibration and verifications of online analyzers
Jar testing alternative water treatment coagulants and filter aids
Monthly, bi-monthly and weekly dam inspections completed
Reservoir vertical profile and submitted samples for lab analysis
R&D of system components for improving current WTP performance
Distributed the 2023 CCR and WUE to the membership
Investigated water pressure and flow at customer property
Replaced BBQ at Clubhouse
Leakage surveying
Received remaining materials for the Cabana restoration project
Ecological Critical Areas Survey conducted at Holiday and Dickinson Lake
Lead Service Line Inventory Survey
Distribution system flushing
Groundskeeping various locations
DOH monthly meeting
➢ The Critical Area Survey was conducted to satisfy the permitting requirements necessary for the reservoir floating dock, new WTP project, and future maintenance tactics being investigated in and around Holiday Lake. Separate reports will be provided by the contracted professional ecological scientists delineating between the two water bodies which will allow for a more streamlined process during the permitting process. Surveying of the flagged data points will be conducted to update the topographic site plan survey provided by Jepson & Associates.
➢ Elm Electric provided an estimate for the installation and connection of 120V power to an aerator pump for Holiday Lake. The proposed work would provide power for a single aerator pump, LISECC supplied and connected, as well as the ability to add an additional pump at a later time. LISECC Staff would be able to install a conduit crossing the road by the WTP grate prior to Elms start date to help lower the overall cost of the project. The addition of a second aerator pump at the far side of the lake would require a buried conduit, encased in concrete, to be installed around the perimeter of the lake. Total length of the conduit trench would be ~ 400 feet, requiring ~ 10 yards of concrete. State and County review of the Ecological Critical Area Survey will determine whether or not installation of the aerator pumps are permissible within the area. Allocation of funds toward this project should be delayed pending State and County review of the proposed plan.
Upcoming Projects:
Optimize coagulation and filtration process Ongoing
Continue leak detection and distribution repairs Ongoing
New WTP review w/ Wilson Engineering Ongoing
Repair Cabana bathrooms Ongoing
Install Marina cameras July, 2024
Install new distribution sampling stations Summer, 2024
Reservoir floating dock Summer, 2024
Filter media replacement Summer, 2024
June 2024 Water Usage (in gallons)
Total Water Produced 412,900 Chlorine monitoring (0.178 gpm) 7,646
Flushing 3,000
Metered Usage 263,600
Other (Chlorine residual testing, BW) 28,840 Authorized Consumption 303,130
System Leakage 109,770
Percentage of loss 26.6% Average gallon per minute loss 2.5