July 27-August 24, 2024 Operations Report
/Nick Kluge, Operations Manager
During this period:
Staff cataloging/mapping of CAA survey markers
Corresponded with multiple state agencies regarding the development of LISECC property
Temporary repairs made to a Clubhouse external wall outlet
Removed damaged Marina bulletin board
Calibration and verifications of online and portable analyzers
Jepson & Associates onsite visit for CAA survey and boundary marking
Jar testing of various alternative water treatment coagulants and filter aids
Hydrant testing for fire flow at the Beach Ave and Holiday Lake standpipe
Monthly, bi-monthly and weekly dam inspections and vegetation clearing complete
Reservoir vertical profiling with lab sample analysis
Working with Kingworks Engineering to finalize the permit requirements for the reservoir dock
R&D of system components for improving the current WTP performance
Cleaned and serviced chemical feed pumps, injection quills, and solution day tanks
Reviewing media replacement plan with DOH engineer and specialists
Site visit with the WA Dept. of Fish and Wildlife, District Biologists, to investigate local bat colony
Began constructing fish cages to protect pipe inlets in the lakes
Sieve analysis of filter media
Weekly leakage surveying
Lead Service Line Inventory Survey
Monthly distribution system flushing
Daily groundskeeping various locations
Vegetation clearing of ditches and culverts at various locations
DOH monthly meeting
Upcoming Projects:
Optimize coagulation and filtration process Ongoing
Continue leak detection and distribution repairs Ongoing
New WTP review w/ Wilson Engineering Ongoing
Repair Cabana bathrooms Ongoing
Install fish cages in the lakes September, 2024
Install Marina cameras September, 2024
Install new distribution sampling stations Summer, 2024
Reservoir floating dock Summer, 2024
Filter media replacement Summer, 2024
July 2024 Water Usage (in gallons)
Total Water Produced 521,700 Chlorine monitoring (0.178 gpm) 7,946
Flushing 3,000
Metered Usage 418,140
Other (Chlorine residual testing, BW) 2,325 Authorized Consumption 431,411
System Leakage 90,289
Percentage of loss 17.3% Average gallon per minute loss 2.0