November 17-December 15, 2023 Operations Report
/Kevin Southworth, Operations Manager
During this period:
Troubleshooting filter performance issues
Calibrated turbidmeters, UVT, CL-10
Backwash optimization
Leakage surveying
Jar testing
Received new coagulant chemical samples for trials
Installed new fire extinguishers
Weekly and monthly dam inspections
Identified leak inside PRV vault at swim lake (1-2 gpm)
Cleaned gutters on WTP
Received and delivered clubhouse TV and sound bar
Community road sweeping
Grounds keeping
Updated contact info on WFI
Renewed: SAM, DOE WTP General Permit, AMTA, ERWOW, DOH Ops Certificates
Upcoming Projects:
DOH onsite visit for filter troubleshooting assistance and jar testing (December 20th, 2023)
Repair leak inside PRV vault (December 2023)
Clubhouse lighting (Pending availability of the electrician)
Install Marina cameras (January 2024)
Update and submit EAP to Dam Safety (December 16, 2023)
Continue leak detection and distribution repairs (Ongoing)
Repair Cabana bathrooms (January-February 2024)
October 2023 Water Usage (in gallons)
Total Water Produced 380,900 Chlorine monitoring (0.178 gpm) 7,690
Flushing 3,000
Metered Usage 241,230
Other (Chlorine residual testing, BW) 2,325 Authorized Consumption 254,245
System Leakage 126,655
Percentage of loss 33.3% Average gallon per minute loss 2.9