Clubhouse Renovations-Progress to Date (4/2/2024)

Foundation Renovations

At this point, the foundation renovations are complete and electrical upgrades are done (there may be some work still pending on outdoor lighting). The contractor is working on framing up the walls for the new mechanical/furnace space and the new outside walls and door in preparation for furnace reinstallation planned for Tuesday, April 9.
 
We’re looking forward to a return to in-person meetings at the LISE Clubhouse for our April Board meeting.