February 2017 Operations Report
/Operations report for February 2017
Water Usage
Pumped 328,240
Backwashes 46,200 (x 1650 gals per backwash)
Net pumped 282,040
Both Kevin and Issac are signing up for the tests by Doh We have a residents questionnaire ready after Kevin takes the CCCS test.
We are finishing work on the docks. We can remove the dock deployment as a category as the expense for that work should be minimal.
We continue to work on making the water usage data more consistent but I have located several problems in data collection that cannot be over come. We read the source meter at 7:00 am ant the pump meter when the pump shuts down In addition the pump meter is including the water being consumed during the pump run. That amount varies considerably especially on weekends.