March 23-April 26, 2024 Operations Report

Kevin Southworth, Operations Manager

During this period:

  • Reservoir tank cleaning and inspection

  • Cabana bathroom floor and frost damage repair

  • Prepping Clubhouse for reopen

  • Groundskeeping

  • CL-10, pH, 2100Q, TU5300, 1720e calibration

  • New calibration standards for Sonde placed on order

  • Leakage surveying

  • Restock supplies in preparation for dry dock

  • Jar testing

  • Filter performance trouble-shooting

  • PM on work truck

  • Maintenance shop organizing

  • Wilson Engineering review

  • DOH monthly meeting

Upcoming Projects:

  • Optimize coagulation and filtration process Ongoing

  • Continue leak detection and distribution repairs Ongoing

  • New WTP review w/ Wilson Engineering Ongoing

  • Repair Cabana bathrooms April, 2024

  • Install gap covers on marina dock sections April-May, 2024

  • Install Marina cameras April-May, 2024

  • Launch Marina Docks May, 2024

  • Install new distribution sampling stations May, 2024

  • Reservoir floating dock Summer, 2024

  • Filter media replacement Summer, 2024

February 2024 Water Usage (in gallons)

Total Water Produced 433,500 Chlorine monitoring (0.178 gpm) 7,946
Flushing 3,000
Metered Usage 255,319
Other (Chlorine residual testing, BW) 64,479 Authorized Consumption 330,744
System Leakage 102,756
Percentage of loss 23.7% Average gallon per minute loss 2.3