November 19-December 15, 2022 Operations Report
/Kevin Southworth, Operations Manager
During this period:
Flushed section 4
Various leaks detected and fixed, recovered ~ 8gpm
Repaired docks water line
Street sweeping and grounds maintenance
Rebuilt raw water sampling manifold in WTP
Repaired frozen reservoir pump back system
Upcoming Projects:
Leak detecting and distribution repairs
Weir design and construction at the reservoir
November 2022 Water Usage (in gallons)
From storage tanks 471,100 Chlorine monitoring feed (0.178 gpm) 7,945
Net to distribution 463,155
Flushing 3,000 Residential meters 230,060
Unaccounted for water 230,095 Percentage of loss 50.0% Average gallon per minute loss 5.3