February 21-March 21, 2022 Operations Report
/Kevin Southworth, Operations Manager
During this period:
Placed caution tape to block south side of Clubhouse deck due to geotechnical engineer’s recommendation limiting activity on that section of the deck.
Received and installed a new controller unit for the turbidimeter.
Clubhouse decks pressure washing completed by Nick Kluge.
Dock repairs and upgrades completed by Chris Immer, including a new winch system for the gangway.
Coming up:
Large docks scheduled for launch on April 19 and/or 20 to be in place for spring dry dock. Small docks will be deployed later in May.
February 2022 Water Usage (in gallons)
From storage tanks 480,500 Chlorine monitoring feed (0.178 gpm) 7,950
Net to distribution 472,550
Flushing 0 Residential meters 234,870
Unaccounted for water 237,860 Percentage of loss 50.3%