May 2018 Operations Report
/Kevin Southworth, Operations Manager
During this month we:
- Installed the new Marina gangway and launched the docks.
- Firewise volunteer work party at the Clubhouse and Marina for Wildfire Community Preparedness Day on May 5.
- Identified two failed customer meters, one of which failed to alert a leak at that address. These meters failed due to exposure and freezing conditions. We have since audited all meters that have not recorded usage in the last six months to determine if there are other failed meters in the system.
- Removed water meter at #30090.
- Repaired leak at Marina blow off valve.
- Asphalt repair at the Marina by Huizenga Enterprises.
- Backhoe brake line repair by Farmer’s Equipment Company.
Water Usage (in gallons)
Pumped 409,320
Backwashes 51,500
Net pumped 357,820
Flushing 5,000
Net to distribution 352,820
Residential meters 311,850
Unaccounted for water 40,970
Percentage of loss 12%